A fatigued portion of the south elevation of the Midland Building fac;ade adjacent to the Lebron James mural In downtown Cleveland was recently secured with engineered safety netting. Not unusual by itself, however Five (RTA) train tracks were immediately below the work area. Extensive planning with the Building Owners And the RTA was required in advance ofthe work. The work was performed by RAM on a Sunday, when RTA was able to provide a twelve (12) hour shutdown of the tracks below. A crane with a manbasket was utilized to access the work area off of Ontario Avenue. The work start was delayed three (3) hours due to
Complications at RTA, but was completed within the window of time provided. The fatigued area remains secured with a proper restoration/reconstruction now in the planning stages.